At Pillar Point Harbor, a dredging project designed to stem erosion at Surfers Beach is finally underway.
Sediment from the launch ramp is currently being dredged and will be redistributed in the west end of the harbor, where a critical eelgrass retransplant will occur to preserve the environment for fish and wildlife, Harbor District Operations Director John Moren said.
That process for eelgrass replanting must be completed by Aug. 15, contractors said previously.
Later this month, Pillar Point Harbor sand will be moved to its final home at Surfers Beach, where erosion is causing concerns for the highway located directly aside the shore.
“We will then shift to pumping the sand along Highway 1 on top of breakwater along to Surfers Beach to restore sediment and sand that naturally would have migrated south,” Moren said.
From around Aug. 7 to Aug. 14, pipeline will be transferred along the highway and down the slope of Surfers Beach to begin the final dredging operation. This could cause delays for pedestrians and cyclists, however, crews will work to allow limited passage when it’s safe, according to a press release from the Harbor District.
Despite minor challenges with keeping the pipe at the mouth of the harbor in place due to strong currents, the project is still slated to be completed by Oct. 15.
The dredging and eelgrass mitigation will cost the Harbor District $5.3 million. A grant from the Ocean Protection Council will directly apply $2.8 million to those construction costs.
In addition, commissioners previously approved the $1.7 million cost of monitoring the project before, during and up to five years after construction. That data collection could be important to pursuing larger dredging projects funded by the U.S. Army Corps of Engineers in the future, a consultant previously told the board.
LORAIN, Ohio — The U.S. Army Corps of Engineers, Buffalo District, will begin dredging operations this week in Lorain Harbor to maintain safe and navigable waterways for Great Lakes commercial vessels, recreational boaters and other harbor users on Lake Erie. The Buffalo District awarded a $2.5 million contract in June 2026 to Michigan-based Walsh Service Solutions… Read More
By: Ire Joe V. C. Laurente CALAPAN CITY, Oriental Mindoro — A priest and environmental advocate of the Calapan City Diocese urged authorities to pause plans to dredge the Alag–Longos River System in Baco town and address first the project’s far-reaching impacts on coastal communities and entire ecosystems. “Reducing flooding is a legitimate goal —… Read More
In order for massive cargo ships and tankers to traverse the Columbia River up to Portland, crews spend up to eight months each year dredging the river bottom so the channel remains deep enough for the commercial ships to pass. The dredging is a massive operation that most people never see. But the work could… Read More
By Leslie Lake BRADENTON BEACH – Dredging crews began work Sept. 9 on a project to restore a nearly mile-long stretch of Coquina Beach with sand that was lost during Hurricane Idalia in 2023. The Coquina Beach Hurricane Idalia Storm Damage Repair Project will place approximately 63,450 cubic yards of sand along about 0.9 miles… Read More
The storm that dropped about three inches of rain on White Crest Beach in Wellfleet Sunday severely damaged the parking lot, dune and steep beach access path. Streams of water took down signs, pieces of asphalt and carved gulleys into the dune cliff. Repairs were scheduled to begin Tuesday, Sept. 15, and the beach is… Read More