At Pillar Point Harbor, a dredging project designed to stem erosion at Surfers Beach is finally underway.
Sediment from the launch ramp is currently being dredged and will be redistributed in the west end of the harbor, where a critical eelgrass retransplant will occur to preserve the environment for fish and wildlife, Harbor District Operations Director John Moren said.
That process for eelgrass replanting must be completed by Aug. 15, contractors said previously.
Later this month, Pillar Point Harbor sand will be moved to its final home at Surfers Beach, where erosion is causing concerns for the highway located directly aside the shore.
“We will then shift to pumping the sand along Highway 1 on top of breakwater along to Surfers Beach to restore sediment and sand that naturally would have migrated south,” Moren said.
From around Aug. 7 to Aug. 14, pipeline will be transferred along the highway and down the slope of Surfers Beach to begin the final dredging operation. This could cause delays for pedestrians and cyclists, however, crews will work to allow limited passage when it’s safe, according to a press release from the Harbor District.
Despite minor challenges with keeping the pipe at the mouth of the harbor in place due to strong currents, the project is still slated to be completed by Oct. 15.
The dredging and eelgrass mitigation will cost the Harbor District $5.3 million. A grant from the Ocean Protection Council will directly apply $2.8 million to those construction costs.
In addition, commissioners previously approved the $1.7 million cost of monitoring the project before, during and up to five years after construction. That data collection could be important to pursuing larger dredging projects funded by the U.S. Army Corps of Engineers in the future, a consultant previously told the board.
Rotterdam, the Netherlands, 15 July 2026 – The Vancouver Fraser Port Authority has announced that TerraMarine, a consortium including Van Oord, Aecon Group, FlatironDragados Canada and Carlson Construction Group, has been selected as the preferred contractor for the Roberts Bank Terminal 2 – Landmass and Wharf progressive design-build project in Delta, British Columbia, Canada. The… Read More
At Meandering Meuse, the client – Water Board Aa and Maas – and Boskalis are not treating sustainable execution as an add-on to flood protection works. Using a stepped approach (see figure on page 24), the team integrates design optimisation, material choices, logistics and electric equipment into one continuous strategy. The result is a project… Read More
The best way to answer this question is to hear it directly from those who use it every day. In this interview, our Australian customer shares their experience with Dragflow’s autonomous dredging solution, discussing why they chose this technology, how the implementation process went, and the benefits they have seen in their daily operations. For… Read More
An impressive aerial view of the Stuyvesant at work in Corpus Christi, Texas, supporting the Corpus Christi Entrance Channel for the U.S. Army Corps of Engineers Galveston District. During the first half of 2026, The Dutra Group removed more than 3 million cubic yards of material to help maintain safe and efficient navigation through this… Read More
By T.n. Alagesh KUANTAN: Building embankment walls without deepening riverbeds will be ineffective in preventing floods, the Sultan of Pahang, Al-Sultan Abdullah Ri’ayatuddin Al-Mustafa Billah Shah, said. The ruler reiterated his call for shallow rivers to be deepened, noting that embankments would be of little use if rivers continued to silt up. “I have always emphasised… Read More