Posted on August 25, 2023
Vilano Beach Renourishment UPDATE +++++ USACE Jacksonville has begun pumping sand on Vilano Beach as its 2023-2024 renourishment cycle gets under way. The crew has begun beach fill at the northern end of the project area and will move south; see this week’s progress map for projected dates per section. Operations will be under way 24 hours a day, seven days a week. The Corps requests that all residents and visitors maintain a sensible distance from active construction sections and exercise caution in and around the Surfside Park staging area to ensure public safety. @SJCFL @st.johnscounty