Planned work to rebuild Ocean City’s beaches could stretch into the start of the 2027 summer season.
But local officials say they are not concerned about the shifting timeline.
The project was planned before September’s nor’easter stripped sand from Ocean City’s beaches and dunes. The sand pumping will also help rebuild the storm-eroded beach, while officials evaluate separate emergency repairs.
The contractor handling the nearly $28 million project had hoped to start before year’s end. But the ship that will pump sand onto the beach must first be taken out of the water for maintenance, with pumping now expected from mid-March through May.
The Army Corps of Engineers still aims to finish pumping before Memorial Day weekend, but the end date remains uncertain and depends on weather, sea conditions and other operational factors, project manager Todd Beser told The Baltimore Sun. Equipment removal and site restoration could stretch into June.
City Manager Terry McGean said the later arrival falls within the contractor’s allowed work window and does not constitute a delay under the contract.
“We have no concerns with the timing of the project,” McGean said.
Great Lakes Dredge & Dock Co. plans to bring in equipment by mid- to late February and use the ship Liberty Island, Beser said.
McGean said replenishment typically takes about 60 days once the dredge arrives. The construction sequence will not be known until closer to its arrival, leaving unsettled which beach stretches could be affected as the season approaches.
The project will place about 982,000 cubic yards of sand to rebuild the engineered beach berm, an elevated stretch of beach that absorbs wave energy and helps protect Ocean City from flooding and storm surge.
The September storm displaced about 160,000 cubic yards of sand from the beach and dune system and damaged beach crossings, fencing and dune vegetation, according to the Corps’ assessment.
Those features fall outside the sand-placement contract’s scope. Maryland has separately requested federal emergency assistance for storm repairs, with approval and funding pending.
McGean said the assessment found no areas needing temporary repairs before the dredge arrives. Normal winter erosion is not expected to change the project’s cost or sand volume, Maryland Department of Natural Resources spokesperson Gregg Bortz said.
The Board of Public Works is scheduled to consider $1.034 million for the state and local share of project management and engineering oversight Wednesday. Bortz said those routine costs were separated from the dredging contract to speed federal procurement.
The $25.77 million dredging contract and $2.2 million in oversight bring the total to nearly $28 million. The federal government pays 53%, Maryland pays 23.5%, and Ocean City and Worcester County each pay 11.75%.
Rep. Andy Harris, who helped secure federal funding for the project, promised after September’s storm to “do whatever it takes” to restore the beach.
“I continue to work closely with the U.S. Army Corps of Engineers to ensure Ocean City’s beach is restored before the summer season begins,” he said.