The third and largest phase of the Port of Progreso expansion is underway, with a massive dredging ship now working off the Yucatán coast.
Gov. Joaquín Díaz Mena announced the start of the federal government’s dredging work, which calls for removing more than 3 million cubic meters (about 3.9 million cubic yards) of material from the seabed. The goal is a deeper port that can take larger ships and move cargo faster.
When the work is done, the port area will grow from 34 hectares to 114 hectares (roughly 84 acres to 282 acres) with the addition of two new platforms.
“We continue creating the conditions to attract investment and boost our economy,” Díaz Mena said.
A familiar ship returns
The job belongs to the Fernando de Magallanes, a cutter suction dredger operated by the Belgian company Jan De Nul. The vessel is no stranger to Progreso. It crossed the Atlantic for the project’s first phase, which deepened the navigation channel and wrapped up in March. The ship made the trip from Europe in about a month.
A cutter suction dredger works like a giant underwater vacuum with teeth. A rotating cutter head loosens the seabed, and pumps push the slurry through pipes to wherever the material is needed. In this case, much of it will help build the new platform.
The current stage focuses on dredging and shaping a 40-hectare (99-acre) northern platform, according to the federal port authority, ASIPONA Progreso. That stage alone calls for removing just over 3 million cubic meters of material.
Federal, state and private funding for the overall expansion totals about MX$7.9 billion (roughly US$425 million).
Three phases, one goal
The project has been a long time coming. Plans to turn Progreso into a true deep-water port have been discussed for about 25 years, and preliminary dredging began in January 2025 in a ceremony led by Mexico’s Navy and Díaz Mena.
There have been bumps along the way. In July, ASIPONA Progreso rejected every proposal in an earlier tender for the northern platform and declared it void.
The expansion has been divided into three parts.
The state government paid for the first phase on its own, investing MX$1.63 billion (about US$88 million). That work deepened the navigation channel from 11.75 meters to 13.30 meters (about 38.5 feet to 43.6 feet).
The second phase focused on the cruise ship area. It was funded with MX$948 million (about US$51 million) in private investment from the company SSA Marine México.
The third phase, led by the federal government, is the most ambitious. Officials have not released a cost breakdown or a completion date for this stretch of the work.
Why it matters
Progreso has long been a fairly minor gateway for trade with the U.S., Latin America and Europe. Its pier stretches about 4 miles into the Gulf of Mexico, and cruise ships remain its most visible traffic.
State officials see the expansion as a way to change that. New platforms would make room for terminals, logistics centers and maritime services, and they hope to lure industrial investment to the region.
The port is also expected to tie into the Tren Maya’s freight service. That rail line is designed to connect Mérida’s industrial zone with Progreso, so goods arriving by sea can move by train across the Peninsula and beyond. Officials have said freight operations could begin between late 2026 and early 2027.
Cruise tourism is part of the picture, too. State tourism officials have projected 171 cruise ship arrivals and more than 520,000 passengers in Progreso this year.
Not everyone has welcomed past port work. Some coastal property owners have blamed earlier pier construction for beach erosion along the coast near Progreso.
Fast Facts
- Project: Third phase of the Port of Progreso expansion
- Dredger: Fernando de Magallanes, operated by Belgium’s Jan De Nul
- Material to remove: More than 3 million cubic meters (3.9 million cubic yards)
- Port area: From 34 to 114 hectares (84 to 282 acres)
- Phase 1: MX$1.63 billion (about US$88 million), paid by the state
- Phase 2: MX$948 million (about US$51 million), private investment
- Phase 3: Led by the federal government; no completion date announced
- Total investment, all phases: About MX$7.9 billion (roughly US$425 million)