Great Lakes Dredge & Dock Co. has announced that the company has made significant progress since the dredge Ellis Island joined the dredge Liberty Island in Buxton on Tuesday, August 2.

These two dredges used two separate landing points, and together they have delivered approximately 200,000 cubic yards of sand along the shoreline of Buxton over the past three days. As of this morning (Friday, August 5, 2022), over 60 percent of the 1.2-million cubic yard contract volume has been placed on the beach, and nourishment in front of the Village of Buxton is now completed. The rest of the volume of sand will be placed north of the Village of Buxton along the Cape Hatteras National Seashore, and the project is expected to be completed by the end of August.

The Ellis Island is expected to continue to use the landing point near the south end of Town Circle in Buxton and pump north until the morning of Saturday, August 6, 2022. The pipes on the beach will be disassembled and removed, and the newly nourished beach is expected to be smoothed and opened to the public by Sunday morning, August 7, 2022. The dredge will then shift to the landing point located approximately 3,000 feet north of the northern boundary of Buxton that the Liberty Island is currently using.

A third landing point that is located approximately 8,000 feet north of Buxton has also been partially installed. Great Lakes Dredge & Dock Co. has scheduled a bull gang to complete the setup of the third landing point tomorrow morning. The Liberty Island will start using this third landing point once the installation is complete. At that time, both dredges will pump north for a few days before switching directions.

Nags Head: Project construction should be finished by early September

Restoration of the southernmost two miles of beach in Nags Head, from about 9405 South Old Oregon Inlet Road south through 10435 South Old Oregon Inlet Road, has been completed.

In mid-to-late August, a second dredge will arrive, and construction will begin near 8701 South Old Oregon Inlet Road and progress south to near 9405 South Old Oregon Inlet Road over about seven days. Then, construction will return to near 8701 South Old Oregon Inlet Road and, over about seven days, proceed north to 8031 South Old Oregon Inlet Road, the northern end of the beach restoration area. Project construction should be completed by early September.

Remember, it is likely the schedule will change over the course of the project.

Duck: Construction to begin in early November

Weeks Marine, the dredging contractor for the beach nourishment project from Kill Devil Hill to Duck, has provided an updated schedule.

As of August 3, the company anticipates that equipment staging will begin in late October, with construction beginning on or near November 4. The construction itself is projected to last 25-30 days.

All time frames are subject to weather, mechanical, and other unforeseen delays. As we receive updates they’ll be posted on our website and at morebeachtolove.com.