The ferry Independence travels between Chebeague and Cousins Island in Yarmouth daily.

During this month alone, the ferry between Yarmouth and the island has been delayed or canceled three times because of blocked access, according to the Chebeague Transportation Company’s website.

“Until the Stone Pier dredging project is completed, cancellations during extreme low tides will, unfortunately, continue,”  the company posted.

Canceled ferry landings began in late 2019 to early 2020 and have only gotten worse over time, Ridgeway said.  In the nine years he has worked for the company, the ferry rarely canceled, and then only in extreme weather and/or abnormally high tides, he said.

Island Commons, a nonprofit assisted living home, has been struggling with the ramifications of cancellations and delays.

“We operate 24/7/365 and most of our caregiving staff commute from the mainland.  They travel from as far as Lewiston and Lisbon and most have at least a 40-minute commute, not including ferry time,” Community Outreach Manager Nancy Olney said. “We hire Fogg Water Taxi out of Portland to transport staff when the CTC boat has low-tide cancellations.  It’s very expensive, but with few on-island caregiving employees, it’s a necessary expense until the channel is dredged.”

Around 34,000 cubic yards of deposits will be removed during the project, according to the Army Corps of Engineers. The dredged material will be taken to the Corps’ Portland Disposal Site about 8 miles off the coast of Cape Elizabeth.

Meanwhile, the town faces the longer-term issue of raising the wharf to accommodate rising sea levels.

Wright-Pierce, hired by the town for $120,000, reported to the Select Board last week that the wharf is stable enough to be raised but modifications would be necessary. Plans have not been finalized and there is no timeline yet for that project.“When we have a storm, the water goes over the wharf,” Damon said. “You can’t see where the water is and where the ocean is when we have high tides and a big storm. So there’s two issues: Is the wharf high enough and is the ocean deep enough?”

Wright-Pierce suggested the town use micropiles, which are steel-encased concrete pilings with a reinforced steel core attached to bedrock, to strengthen and lift the wharf. The pilings would lift the pier about 2-3 feet. Once the pier is lifted, the parking area and drop-off zone will also need to be reconfigured, engineer Jason Gallant said.

Wright-Pierce also suggested extending the boat ramp farther seaward by about 20 feet to access deeper water.

The next steps are to create a draft report and hold public meetings so options can then be weighed to decide what solutions will best serve the community and at what cost, Gallant said.

When asked about associated costs, Wright-Pierce staff said they did not want to venture any guesses. It will depend on available funds and grants and the cost of parts and labor at the time of construction.