Posted on November 23, 2026
By Ana Alice
Building a passage beneath the Port of Santos shipping channel, used by some of the world’s largest ships, will pose a challenge that goes well beyond engineering. To install Brazil’s first immersed-tube tunnel, the project calls for temporarily halting navigation at the country’s largest port complex.
The operation is part of the construction of the Santos-Guarujá tunnel, a project estimated to cost R$6.8 billion, which is expected to transform the connection between the two cities on the coast of São Paulo state.
Under the concession documents, the channel could be closed six times, for periods of 48 hours, for a total of 288 hours of interruptions. That amounts to 12 days in all, but does not mean ships will be unable to pass for nearly two consecutive weeks.
The operations are scheduled for 2029, when massive concrete structures will be transported to the channel and installed on its bed. The plan could still be adjusted to coordinate construction with port operations.
Why will the Port of Santos shipping channel need to be closed six times?
The reason lies in the construction method chosen for the connection. Unlike a conventional tunnel, bored through the ground by excavation machines, the passage between Santos and Guarujá will be made from large concrete modules built out of the water.
The reference design calls for six of these structures. Each will need to be transported to the installation site, positioned and carefully lowered until it reaches the channel bed.
Ship traffic could be interrupted during these maneuvers. The procedures involve tugboats, positioning equipment and operations that must take place without interference from large vessels.
The second clarification document for the tender, released by the São Paulo state government, sets out a reference plan of six 48-hour windows, with intervals of about 15 days between operations.
Together, the interruptions add up to the 288 hours specified in the plan. The document also allows a different schedule to be agreed upon by the responsible authorities and the concessionaire.
Before carrying out activities that could affect navigation, the company must submit a restriction plan to the Regulatory Agency for Delegated Public Transport Services of the State of São Paulo (Artesp) at least 60 days in advance.
The plan will have to be reviewed by the agency and approved by the Santos Port Authority (APS).
This means the dates and final duration of the interruptions will still depend on the organization of operations and the necessary authorizations.
How six massive concrete modules will form an underwater tunnel
The technique used is known as an immersed-tube tunnel. Although new to Brazil, it has already been used in major infrastructure projects in Europe and Asia.
The process begins on land, where the modules are built in a dry dock. The sections undergo strength and watertightness tests before being prepared for transport.