Posted on November 16, 2026
Once in a while, citizen volunteers serving on government advisory committees get to see the fruits of their labor play out, as the Dare County Waterways Commission witnessed with the recent implementation of the emergency ferry channel after storms in both September and October. Although the success of the backup transportation plan was a group effort, the commission more than two years earlier had first brought attention to the shoaled channel and continued to clang alarms to secure its accessibility.
“Big shout-out and thank you to the Ferry Division for getting the ferries up and running,” Commission Chair Steve “Creature” Coulter said at Monday evening’s meeting in Manteo. “Everything seemed to run smoothly.”
Member Natalie Kavanagh also voiced her appreciation, saying that the division doubled the number of inspection trips using ferries to ensure the channel was still navigable.
“I’m grateful that the Ferry Division agreed to check the ferry channel every quarter,” she said.
First created in 2009 after previous events had blocked travel on the island’s only highway, leaving islanders trapped for days, the emergency channel between Rodanthe and Stumpy Point on the mainland was last used in December 2013. But after the recent back-to-back nor’easters, which each damaged pavement and destroyed dunes on a section of N.C. 12 across from the Pea Island Visitor Center, the ferries started operating 24 hours a day, each time transporting thousands of people and vehicles off and on the island over multiple days.
But back during its July 2024 meeting, the Waterways Commission first learned that a relatively small shoal in the Rodanthe Harbor basin, with about 5 feet of water in the bad spot, was creating a controlling depth that rendered the entire emergency channel unnavigable. The rest of the emergency channel had about 6 feet of water, but ferries have a draft of 5.5 feet.
At the news, commissioners unanimously reacted with what essentially amounted to a loud “WHAT?!,” noting with disbelief the vulnerability of the island as the height of storm season approached.
“This needs to be very clear to our county commissioners,” member Ernie Foster had said. “Emergency operations right now do not exist and (it’s) hurricane season.”
Over subsequent meetings, entangled jurisdictional responsibilities between the county, the state and the local governments seemed to stall progress, but commissioners continued to insist that a solution had to be found sooner rather than later.
Although Dare County in September 2024 had paid to have the shoal cleared out with a bucket-and-barge project, it was eventually agreed that permitting needed to change to allow timely responses. The goal was to find a long-term solution to maintain the channel’s availability year-round in case of emergencies, but bureaucratic roadblocks frustrated fast remedies.
“We were very fortunate to dodge a major bullet,” member Danny Couch commented that November.
And it was only the luck of quiet hurricane seasons that followed in 2025 and 2026 — until the nor’easters unexpectedly tore up the road in one-two punches — that provided the runway the county needed to get a long-term plan in place. Working closely with Dare County dredge consultant Ken Willson, with Coastal Planning & Engineering of North Carolina, an agreement was reached with state and local partners for the U.S. Army Corps of Engineers — which has authority over the federal Rodanthe Harbor and the channel up to Stumpy Point basin, a state channel — to permit Dare County to use its local dredge, the Miss Katie, or any other available and appropriate dredge to maintain the emergency channel as needed.
Commission administrator Barton Grover told members at Monday’s meeting that the county is close to having the permit in hand.
“We have the CAMA permit, we don’t have the Corps permit yet,” he said.
In a later interview, Grover explained that a contractor has been hired to conduct a required cultural resources survey of a portion of the emergency channel. He expects the permit could be issued within a week or so, conditioned on the results of the survey. But if the problem spot suddenly needed attention before those results were provided, he said, it would be able to be dredged because that area has already been surveyed.
With just 6 feet of water in the channel now, Coulter said there is very little cushion available for ferries until the county is able to dredge the channel to 8 feet plus 2 feet of additional depth. Unrelenting northeast winds during the recent storms played havoc with the depths, he noted.
“It was 2.5 feet higher in the emergency ferry channel during the first event,” he said.
“That wasn’t the case with the second outage,” he said, adding that it was at least a foot lower. “A hurricane could very easily suck every bit of water out of that channel.”
As far as the few glitches during the emergency ferry operations that were raised during the meeting, Grover confirmed that they have been addressed. Gantries at ferry dock ramps on each side were found to be not high enough to accommodate some of the large vehicles, but after it came to the Ferry Division’s attention during the first event, both sides were elevated so the trucks could avoid bumping the top. The need for additional lighting was also evident, which both sides now have, he added.
Also, the two pieces of dredge pipe left behind in Stumpy Point basin that damaged a ferry at the end of the second operation have been removed by the Corps, Grover said. The Corps had surveyed the basin after the incident and determined that the pieces were from an old dredge project.
And parking on either side for people using the ferries as pedestrians has also been addressed, Commissioner Mary Ellon Ballance said, adding that the solution lagged initially.
“It will be done right away next time,” she said, adding that parking areas will be available on both sides. “As frustrating and challenging as this is, this one lasted a lot longer than we’d like. I think each time we learn a little more.”