USACE Seattle District to Award FY26 Willapa Harbor Dredging Contract

Posted on October 22, 2025

Introduction

The U.S. Army Corps of Engineers (USACE) Seattle District has announced plans to award the upcoming FY26 Willapa Harbor dredging contract, aimed at maintaining critical navigation routes across Washington’s coastal waterways. This initiative ensures the long-term navigability and safety of the Bay Center, Nahcotta, and Tokeland Federal Navigation Channels.

Project Scope

The Willapa Harbor dredging project involves removing approximately 180,000 cubic yards of material from the three key harbor locations. The dredging work will be carried out using mechanical clamshell dredging methods to restore each area to its authorized depth, supporting efficient commercial and recreational vessel movement.

Timeline and Work Windows

According to the Seattle District, the in-water work period for the FY26 dredging contract varies by location:

  • Tokeland Marina: July 16, 2026 – February 15, 2027
  • Nahcotta: July 16, 2026 – February 1, 2027
  • Bay Center and Palix River: July 16, 2026 – September 30, 2026

These timelines have been designed to minimize environmental impact while maintaining the operational readiness of the harbor.

Industry Collaboration

Earlier this year, USACE hosted a Virtual Industry Day to engage with private contractors and share details about the upcoming FY26 Willapa Harbor dredging opportunity. The event aimed to foster collaboration and transparency as part of the federal government’s broader efforts to maintain vital maritime infrastructure.

Conclusion

The FY26 dredging contract for Willapa Harbor marks another important step in the USACE Seattle District’s ongoing commitment to sustaining Washington’s coastal waterways. Once awarded, this project will help ensure the continued accessibility and reliability of the harbor for years to come.