It's on us. Share your news here.

Sh. Narudhoo Harbor Development Project well underway

Sh. Narudhoo Harbor Development Project

Posted on August 14, 2023

Maldives Transport and Contracting Company (MTCC) has disclosed that the Harbor Development Project of Narudhoo Island in Shaviyani Atoll is well underway.

MTCC states that the company has completed installation of blocks required for quay wall construction under the project.

Currently ongoing at the site are quay wall concrete works and the new harbor basin dredging operations.

The second shipment of concrete blocks required for quay wall construction for Narudhoo Harbor Development Project was delivered to the site on 17th July 2023.

The company kicked off the physical work for the harbor development project 4 May, 2023.

Under the scope of the project MTCC is required to conduct harbor dredging operations in an area measuring 51,212 cubic meters as well as channel dredging operations in an area of 4,120 cubic meters.

The construction of a quay wall measuring 210 meters, a 371-meter breakwater and a revetment measuring 205 meters also come under the scope of the project.

Further, MTCC will also be installing harbor lights as well as a harbor pavement measuring 955 square meters and constructing a ramp under the project.

The value of the project is MVR 41.34 million.

Source

It's on us. Share your news here.
Submit Your News Today

Join Our
Newsletter
Click to Subscribe