The harbor development project in Maaungoodhoo island of Shaviyani atoll is well underway.

This was revealed by the Maldives Transport and Contracting Company (MTCC) on Sunday.

As such, taking to social media platform ‘X’ to provide the latest updates of the Maaungoodhoo harbor development project to the public, MTCC revealed that the project has reached overall 53 percent progress.

MTCC most recently completed the construction of a quay wall block, under the project.

The company went on to reveal that all rock boulders required for the project have arrived at the site, and they are currently working to unload them.

Under the scope of the project, MTCC is required to conduct dredging operations in an area measuring 59,013 cubic meters and channel dredging operations in an area measuring 3,245 cubic meters.

The construction of a ramp, a concrete jetty, a breakwater measuring 362 meters, a quay wall measuring 312 meters and a 105-meter revetment also comes under the scope of the project.

The project also entails the installation of a harbor pavement measuring 1,509 square meters, harbor lights as well as mooring buoys.

The Maaungoodhoo harbor development project is valued at MVR 56.79 million.