At Pillar Point Harbor, a dredging project designed to stem erosion at Surfers Beach is finally underway.
Sediment from the launch ramp is currently being dredged and will be redistributed in the west end of the harbor, where a critical eelgrass retransplant will occur to preserve the environment for fish and wildlife, Harbor District Operations Director John Moren said.
That process for eelgrass replanting must be completed by Aug. 15, contractors said previously.
Later this month, Pillar Point Harbor sand will be moved to its final home at Surfers Beach, where erosion is causing concerns for the highway located directly aside the shore.
“We will then shift to pumping the sand along Highway 1 on top of breakwater along to Surfers Beach to restore sediment and sand that naturally would have migrated south,” Moren said.
From around Aug. 7 to Aug. 14, pipeline will be transferred along the highway and down the slope of Surfers Beach to begin the final dredging operation. This could cause delays for pedestrians and cyclists, however, crews will work to allow limited passage when it’s safe, according to a press release from the Harbor District.
Despite minor challenges with keeping the pipe at the mouth of the harbor in place due to strong currents, the project is still slated to be completed by Oct. 15.
The dredging and eelgrass mitigation will cost the Harbor District $5.3 million. A grant from the Ocean Protection Council will directly apply $2.8 million to those construction costs.
In addition, commissioners previously approved the $1.7 million cost of monitoring the project before, during and up to five years after construction. That data collection could be important to pursuing larger dredging projects funded by the U.S. Army Corps of Engineers in the future, a consultant previously told the board.
C&C Marine & Repair has successfully lifted and set the ladder and A-frame onto our nearly completed 30-inch spec cutter suction dredge. Projects like this reflect the skill, coordination, and craftsmanship of the team behind every build at C&C Marine & Repair. We look forward to sharing more as the project moves closer to completion…. Read More
By Sylvia Schandert Dredging operations in the Itajaí-Açu River channel began this Saturday, April 4, 2026. The operation was monitored by the Itajaí Port Authority starting at 7:30 a.m. and marks the beginning of the work outlined in the contract signed with Van Oord, which is responsible for the maintenance dredging of the waterway access… Read More
OKATIE — The Post and Courier’s Rising Waters Lab and the Coastal Community Foundation will host a forum on coastal resilience April 8 at the Port Royal Sound Maritime Center. The event, “Balancing Conservation and Development in the Port Royal Sound,” begins at 6 p.m. Doors open at 5:30 p.m. at 310 Okatie Highway. The Port Royal Sound watershed contains… Read More
Deer Run Golf Course in Brillion, Wisconsin has struggled with severe flooding for years, with the owner having to install a pump to try to move water off the green. The Department of Natural Resources (DNR) and Ducks Unlimited plan to begin a dredging project this spring to address the ongoing water issues, removing excess… Read More
The North Carolina Coastal Resources Commission is to meet next week to consider proposed language amendments for inlet hazard areas. The meeting for the commission, which establishes policies for the N.C. Coastal Management Program and adopts rules for both the Coastal Area Management Act and the N.C. Dredge and Fill Act, will begin with a… Read More