At Pillar Point Harbor, a dredging project designed to stem erosion at Surfers Beach is finally underway.
Sediment from the launch ramp is currently being dredged and will be redistributed in the west end of the harbor, where a critical eelgrass retransplant will occur to preserve the environment for fish and wildlife, Harbor District Operations Director John Moren said.
That process for eelgrass replanting must be completed by Aug. 15, contractors said previously.
Later this month, Pillar Point Harbor sand will be moved to its final home at Surfers Beach, where erosion is causing concerns for the highway located directly aside the shore.
“We will then shift to pumping the sand along Highway 1 on top of breakwater along to Surfers Beach to restore sediment and sand that naturally would have migrated south,” Moren said.
From around Aug. 7 to Aug. 14, pipeline will be transferred along the highway and down the slope of Surfers Beach to begin the final dredging operation. This could cause delays for pedestrians and cyclists, however, crews will work to allow limited passage when it’s safe, according to a press release from the Harbor District.
Despite minor challenges with keeping the pipe at the mouth of the harbor in place due to strong currents, the project is still slated to be completed by Oct. 15.
The dredging and eelgrass mitigation will cost the Harbor District $5.3 million. A grant from the Ocean Protection Council will directly apply $2.8 million to those construction costs.
In addition, commissioners previously approved the $1.7 million cost of monitoring the project before, during and up to five years after construction. That data collection could be important to pursuing larger dredging projects funded by the U.S. Army Corps of Engineers in the future, a consultant previously told the board.
Our U.S. Army Corps of Engineers, NY District is removing approximately 550,000 cubic yards of sand material from the East Rockaway Inlet in Queens, N.Y. This dredging project will not only provide safe navigation for the community, but the sand material being removed will be beneficially reused as beach renourishment along the Far Rockaway Beach… Read More
Skandi Minder at the quay at Vard Langsten. Skandi Minder has arrived at Vard Langsten for an aftermarket project for DOF. Designed for field installation operations across a wide range of water depths and conditions, the project is a strong match with Vard Langsten’s capacity and competence. The scope includes interior repairs, ROV/LARS installation, main engine overhaul,… Read More
Work is underway on Oceanside’s Coastal Dune Restoration Pilot Project at spots along North Harbor Beach, North Strand, and the San Luis Rey River mouth. Crews are installing fencing and planting native Pink Sand Verbena seeds harvested from Camp Pendleton. The restored coastal dunes will provide low-cost coastal resilience against storm events and high wave surf,… Read More
Massachusetts Department of Environmental Protection BOSTON — The Healey-Driscoll Administration today announced more than $2 million in new funding to restore and monitor salt marshes along the Massachusetts’ coastline. Salt marshes protect communities from flooding, prevent damage from storms and rising seas, serve as habitat for fisheries and wildlife, and absorb carbon that would otherwise contribute… Read More
Palm Beach’s coastline continue to gain sand, thanks dredging and sand and dune-nourishment efforts, the town’s coastal engineering consultant told the Shore Protection Board during its recent meeting. During the Jan. 8 meeting, Mike Jenkins said Palm Beach’s 12.2 mile-shoreline has gained 5.75 million cubic yards of sand since the town first started measuring long-term sand volumes… Read More