At Pillar Point Harbor, a dredging project designed to stem erosion at Surfers Beach is finally underway.
Sediment from the launch ramp is currently being dredged and will be redistributed in the west end of the harbor, where a critical eelgrass retransplant will occur to preserve the environment for fish and wildlife, Harbor District Operations Director John Moren said.
That process for eelgrass replanting must be completed by Aug. 15, contractors said previously.
Later this month, Pillar Point Harbor sand will be moved to its final home at Surfers Beach, where erosion is causing concerns for the highway located directly aside the shore.
“We will then shift to pumping the sand along Highway 1 on top of breakwater along to Surfers Beach to restore sediment and sand that naturally would have migrated south,” Moren said.
From around Aug. 7 to Aug. 14, pipeline will be transferred along the highway and down the slope of Surfers Beach to begin the final dredging operation. This could cause delays for pedestrians and cyclists, however, crews will work to allow limited passage when it’s safe, according to a press release from the Harbor District.
Despite minor challenges with keeping the pipe at the mouth of the harbor in place due to strong currents, the project is still slated to be completed by Oct. 15.
The dredging and eelgrass mitigation will cost the Harbor District $5.3 million. A grant from the Ocean Protection Council will directly apply $2.8 million to those construction costs.
In addition, commissioners previously approved the $1.7 million cost of monitoring the project before, during and up to five years after construction. That data collection could be important to pursuing larger dredging projects funded by the U.S. Army Corps of Engineers in the future, a consultant previously told the board.
By Timothy O’Hara Florida sea turtles in the past five years have laid over 14,000 nests on two St. Lucie County beaches currently undergoing massive sand replenishment projects, which are occurring during the start of nesting season. Crews with heavy equipment and portable lights are working day and night, seven days a week, to finish…. Read More
By Angie Angers MADEIRA BEACH, Fla. — More than one month into the long-awaited dredging project in John’s Pass, the city of Madeira Beach confirms the contractor is only about 20% complete. A spokesperson for the city said it’s a “slow process” as the contractor, Bayside Dredging, works to pull roughly 13,000 cubic yards of… Read More
SANIBEL, Fla. (WINK) — A large sandbar has effectively sealed off Blind Pass, the waterway that separates Sanibel and Captiva islands. The pass, which typically allows water to flow between the Gulf and the bay system, is currently blocked by a large amount of accumulated sand. Officials say the situation reflects the natural dynamics of a… Read More
DredgeWire note: Great Lakes Dredge & Dock was prime on this project Gov. Jenniffer González Colón and Puerto Rico Aqueduct and Sewer Authority (PRASA) Executive President Luis Reinaldo González Delgado announced over the weekend the completion of the dredging project for the Carraízo Reservoir. They also announced the allocation of funds for a second phase… Read More
SULLIVAN, Ind. (WTWO/WAWV)— The Sullivan County Commissioners met to discuss a number of different topics and one of those items was the current dredging project going on at Sullivan County Park and Lake. Officials with the Sullivan County Park and Lake were asking for the dredging project to be given priority status in the county…. Read More