Posted on November 16, 2026
By Aaron Morby
The Defence Infrastructure Organisation has unveiled plans to replace the ageing 650m-long structure in one of the biggest marine construction projects planned for the Royal Navy.
Built in the 1950s and 1960s, Fountain Lake Jetty provides vital tidal maintenance berths for the Navy’s surface fleet but has reached the end of its working life.
The replacement is needed to accommodate a new generation of larger escort warships supporting the UK’s aircraft carrier strike group.
The scheme will ultimately provide three tidal maintenance berths, up from the two initially required.
The rebuild will be delivered in four phases, covering the 375m eastern section and 275m western section of the jetty.
Work will include extensive demolition, construction of new piled jetty structures, dredging, replacement buildings and upgraded water, power and communications infrastructure.
Contractors will also strengthen and raise existing impounding walls, provide new access routes and carry out flood defence improvements.
The successful contractor will support the project team in developing the preferred design and securing marine licences, as well as delivering the main works.
The investment forms part of the wider Project Royal Oak programme to modernise Britain’s naval bases and improve maintenance facilities for the surface fleet.
DIO plans to issue a market engagement questionnaire before the end of this year, followed by an industry day during the first quarter of 2027.
Formal tenders are scheduled to be invited in June 2027, with the main contract expected to run from March 2028 until December 2037.
The competition will be open to contractors from NATO member countries.
Firms have until 26 February 2027 to respond to the preliminary market engagement exercise.