Matarbari Port project completes 3.6m cubic metres of dredging: Shipping Minister

Shaikh Rabiul Alam

Posted on November 18, 2026

The Matarbari Port Development Project is progressing as scheduled, with around 3.6 million cubic metres of dredging completed so far, Shipping Minister Shaikh Rabiul Alam told parliament on Tuesday.

He said work on two of the project‍‍`s three main packages had already started, while construction activities were continuing at the site.

The minister made the remarks in response to a written question from treasury bench lawmaker Mohammad Mazharul Islam of Kishoreganj-1 in the Jatiya Sangsad, with Speaker Hafiz Uddin Ahmad, Bir Bikrom, presiding.

On Package-1, which covers civil works for port construction, the minister said the project authorities issued a Notice to Proceed (NTP) to contractor PT JV on August 31, 2026.

Necessary equipment for land reclamation has already reached the project site. Construction of Geotube embankments, dredging, sand filling in Areas A and B, and ground improvement works using the CDM method are also underway, he added.

Regarding Package-2A, which covers equipment, the Terminal Operating System (TOS) and security systems, Shaikh Rabiul Alam said preparations of designs and drawings by Japan‍‍`s Mitsui E&S and Tec International Consortium had reached the final stage.

A factory survey was also conducted in Japan from April 4 to 11 to assess the equipment manufacturing capacity.

On Package-2B, covering boats and the Vessel Traffic Management and Information System (VTMS), the minister said a meeting with a JICA delegation was held at the Shipping Ministry on September 2.

The meeting decided to seek bidders‍‍` opinions on extending the tender validity period and bid security, as well as reducing the scope of the tender, to speed up the procurement process.

The minister said the project is scheduled for completion by December 2029, dismissing concerns over delays in establishing the seaport.

Once operational, Matarbari Port will be able to accommodate large container vessels with a capacity of up to 8,200 TEUs at its jetty.