Posted on November 24, 2026
Harbor dredging on Block Island still cannot go out to bid, with a Jan. 31 deadline to finish the work, a harbors staff member told the New Shoreham Harbors Committee at its Thursday meeting, according to the New Shoreham Harbors Committee’s published meeting recording.
Dredging clears built-up sand from harbor channels and docking areas so boats can get through. The staff member said the project is now squeezed into what they called a very small window.
Why it is delayed
The staff member said harbors staff met with the town engineers and that the engineers “were stuck with the permitting process with Army Corps,” because more permits were required than expected. The staff member said that has limited the town to a very small window, and that the town is still waiting on approval of a certain permit before the work can even be put out to bid.
“The surveying was done way too late. They should have done that in the spring,” the staff member said. The staff member said they had anticipated the job going out to bid in August or September, but the survey was not done until the end of September. “Now they’re rushing to get it all done and all the permits through,” the staff member said.
The staff member confirmed the dredging is not under contract. “We have until January 31st to be able to dredge,” the staff member said.
At the committee’s Oct. 15 meeting, as reported in this publication’s coverage, a speaker said dredging would occur this winter and that the town was then waiting only on its engineers to finish permitting.
Trucking versus pumping the sand
The staff member said the dredged sand will likely be trucked and will go to the beach. The staff member said they had “talked about the pump system till I was blue in the face,” calling pumping the most economically advantageous option because the material would not be handled twice.
Committee discussion turned to where the sand should end up. One speaker said it would be a shame to put it out in the ocean instead of on the beach, and said at high tide there is no beach. Another remark noted that at one beach, “it’s all water.”
Who pays
The staff member said all dredging comes out of the harbors budget, even though placing the sand on the beach benefits beach nourishment, the practice of adding sand to eroding shorelines.
“Where are the departments or the other committees? Where’s their money?” the staff member asked. “They should be supporting the dredging projects that I am trying to do.” The staff member said that with the money they are limited to in their budget, they should be getting more from other areas that benefit from the work, adding, “That’s just my opinion.”
No vote was taken on dredging or its funding.
Planning document
Separately, a committee member suggested the town’s harbor hazard mitigation plan recognize sand filling Old Harbor’s inner basin as a significant issue, noting it causes dredging and loss of income. Members discussed adding a bullet point under the plan’s goals, and a speaker said dredging would likely need its own small section. Staff said they would return to a future meeting with proposed language.
What’s next
The dredging must be permitted, bid and completed by Jan. 31, according to the staff member. The committee expects to continue its review of the harbor plan at future meetings.