With a view to remove sediments from the reservoir of the Salal hydropower project situated in Reasi district, the NHPC had floated an open tender in July this year. The primary objective of this comprehensive sedimentation management strategy was mitigating the adverse impacts of accumulated sediments on the critical underwater components of turbines, the water conductor system, and other associated infrastructure of the Salal Power Station.
Work is likely to start on the sediment removal in the coming days and may take over 27 months (more than two years) to complete.
The Salal dam reservoir initially had a capacity of over 284 Million Cubic Metres (MCM) of water. However, over the past few decades, the storage capacity got reduced to less than 14 MCM due to sediment deposition in the main lake. This means a total loss of holding capacity of around 95 per cent has been seen over this time.
Once the sediment removal is done under this project, the reservoir capacity will go up by an estimated 165 MCM, with its total capacity touching 180 MCM. This will be 20 times the present holding capacity of 14 MCM and help partially restore the reservoir’s capacity, thereby substantially enhancing the operational efficiency, power generation capabilities, and overall longevity of the Salal Power Station.
Given the dynamic fast flowing nature of the Chenab River, characterized by high river discharge, especially during the monsoon season (June to September), a well-planned and adaptable sediment removal strategy has been worked out. This strategy incorporates effective flushing operations and takes into account the varying characteristics of sediments deposited across the reservoir.
Duly recognizing that coarser sediments typically settle in the upstream reaches of the reservoir, while finer materials tend to accumulate closer to the dam, the sediment removal plan envisioned that the reservoir be strategically divided into different zones. This zoning approach will facilitate the execution of sediment removal operations in a more structured, efficient, and targeted manner.
Such an approach will enable the application of tailored sediment removal techniques within each section. It will also take into account crucial factors such as the specific type and distribution of deposited material, site accessibility limitations, operational feasibility, and paramount safety considerations.
Sediment Removal and Disposal
This will involve the comprehensive removal and appropriate disposal of various types of sediments, including silt, sand, clay, pebbles, cobbles, and boulders. A critical aspect of this component is the identification and allocation of suitable disposal areas.
It may be mentioned here that the Indus Waters Treaty (IWT) is a treaty signed between India and Pakistan on September 19, 1960, at Karachi. For India, it was then Prime Minister Pandit Jawaharlal Nehru who signed it and for Pakistan, it was done by General Ayub Khan.
Last year, on April 23, Indian Prime Minister Narendra Modi decided to put the IWT in abeyance after the Baisaran (Pahalgam) attack which claimed the lives of 24 male Hindus. Despite Pakistan shouting from rooftops telling the world, or whichever country cares to listen, that India is violating the IWT as there is no provision in it for unilateral suspension.
The issue has been raised or referred to by both warring sides at the United Nations, the comity of nations which is nowadays like an old man/woman in the house to whom nobody listens. This is a sparring match between India and Pakistan which representatives of most nations find utterly boring and repetitive. Yet, it continues to be raised every now and then by Pakistan and Indian representatives use the right to reply to rebut flimsy Pakistani claims.
This has created a circular discourse on the issue with no end in sight. India has said that any review of its decision to put the IWT in abeyance is contingent upon Pakistan giving up terrorism. Not only that, our western neighbour has to provide verifiable proofs that it has stopped fostering terrorism against India! This is something that Pakistan cannot do as it has to first concede that it was fostering terrorism against India! Then prove that it has stopped doing so now.
IWT as an impediment to India’s works
The IWT 1960 acted as an impediment for any works India wanted to undertake on the Chenab, the Jhelum and the Indus. However, putting the IWT in abeyance has led to a slew of decisions from the Central government, mainly regarding projects on Chenab.
The last over 18 months of the treaty being in abeyance has helped speed up work on many projects. The sediment removal from the Salal dam is one of the first such projects which was conceived once the treaty had been put in abeyance.
Incidentally, putting the IWT in abeyance has given us so many advantages. First and foremost is that now we are developing projects on the Western Rivers unimpeded and these projects would have been stalled by Pakistan. Work on 850 MW Ratle project is being done at a pace and in an uninterrupted manner which would have been unthinkable earlier (means before the treaty was put in abeyance).
Mega Sawalakote project may start soon
Starting work on the largest electricity project on the Chenab, the 1,856 MW Sawalakote project, is now a matter of time. The mandatory certificates from various departments are being processed these days. Firm allocation of funds, type of machinery, consultants, shortlisting contractors etc is all being done. Earlier, it was because of Pakistan’s objections that this project got repeatedly stalled. With the IWT in abeyance, all decisions taken now regarding the Sawalakote project have been put beyond Pakistan’s manipulations and objections by the Modi government.
On November 2, a large medical camp was organised by the Sawalakote management team of NHPC at Tanger, headquarters of the project located in Ramban district.
Work on several other projects is also being undertaken on the Chenab and the Jhelum rivers. All this is bad news for Pakistan given its habit of trying to stall everything and anything that India tried to do in the past regarding development of these rivers.
Mega boost for Salal dam capacity
One of the most heartwarming news is regarding the Salal hydropower project of 690 MW capacity. It was a victim of Pakistan’s objections and in April 1978, it suffered a serious setback. All because of the understanding reached then between Atal Behari Vajpayee and Aga Shahi of Pakistan, Salal suffered.
The sluice gates of the project for clearing sediments were plugged with concrete. Between then and now, a period of almost four decades has lapsed and sediments filled the dam all this time. So much has been the deposition of sediments in the reservoir that its holding capacity was reduced from 284 Million Cubic Meters (MCM) to less than 15 MCM, a loss of nearly 95 per cent!
The good news, or the very good news, is that these gates meant for sediment clearing will now be unplugged. The contract for these works will be awarded by NHPC soon and the work will start.
Once the work of unplugging of sediment clearing gates is cleared, a very substantial amount of sediment (sand, driftwood, pebbles and clay etc) will get flushed out from the reservoir. The net impact of this action will be enhancement in the water holding capacity of the Salal reservoir.
Right now, the officials dealing with the subject of sediment clearing are not willing to hazard any guesses as to how much of sediments will get flushed out once the gates are unplugged. Once sediments start getting flushed out, huge deposits of sand, clay, driftwood and other material can/will become a source of revenue for J&K government.
We know for sure that Salal’s water holding capacity decreased from an initial 284 MCM to 15 MCM. For obvious reasons, those who unplug the sediment clearing gates at Salal will want to restore as much capacity as they could. Yet, it is unlikely to go back to its holding capacity at the beginning of the project.
One very positive aspect of sediment removal from the Salal dam will be percolation of water into underground aquifer/s. This will also improve once the sediment clearing is taken up in right earnest.
Incidentally, Pakistan faced a shortage of two million tonnes of wheat this year. In the wheat growing season of 2025, there was no shortage of water supply in Pakistan as Mangla and Tarbela dams were full. In the year 2026, the official water regulator in Pakistan, Indusiver System Authority (IRSA) has reported a 22 per cent deficit of water in Mangla and Tarbela dams. Lesser water will thus impact wheat production this year and accentuate Pakistan’s problems.
Lesser production of wheat, higher costs and likely inflation will all impact Pakistan hugely in the coming months. It needs to be stressed here that the deficit of water availability in the current wheat growing season in Pakistan is not due to result of some Indian action. Yet, villifying India is something that Pakistan will do and we have to answer its false narrative.
The IWT 1.0, the treaty signed in September 1960, is dead as a Dodo. Let us see if an IWT 2.0 comes into being.