Cleveland Harbor Fall Dredging Completed in Just Over Two Weeks; Completes $11.7M Annual Operation

Posted on November 16, 2026

The U.S. Army Corps of Engineers, Buffalo District, completed fall dredging of Cleveland Harbor in just over two weeks, ensuring safe and navigable waterways for Great Lakes commercial vessels, recreational boaters and other harbor users on Lake Erie.

The work was completed 43% sooner than planned – in similar fashion to the efficient dredging completed earlier this year in Conneaut and Lorain – and brings this year’s $11.7 million dredging operation in Cleveland to a close. Dredged sediment from Cleveland Harbor is being recycled, beneficially used and stored using Port of Cleveland facilities.

“Completing this fall’s dredging of 60,000 cubic yards in Cleveland Harbor in just 17 days is another mark of efficiency, good stewardship of American taxpayer dollars, and the dedication to mission the Corps of Engineers is known for,” said Lt. Col. Aaron Anderson, commander of the Buffalo District. “With this work complete, we’re able to turn our focus to more dredging across Ohio and Lake Erie to keep ports thriving, waterways safe, and the U.S. economy strong.”

Fall dredging started Oct. 26 and was completed Nov. 11 as part of an $11.7 million contract awarded in April 2026 to New York-based DMYLES, Inc. for all 2026 dredging in Cleveland.

Fall dredging removed approximately 60,000 cubic yards of sediment from the federal navigation channel in the upper Cuyahoga River, including 10,000 cubic yards added to the contract to address critical areas of shoaling and support local industry needs.

Of the approximately 260,000 cubic yards of sediment dredged from Cleveland Harbor in 2026, 110,000 cubic yards were beneficially used through recycling at the Port of Cleveland’s sediment processing management facility, and 150,000 cubic yards were placed in the port’s confined disposal facility 12.

Dredging of Cleveland Harbor is conducted twice annually by USACE, based on need and the availability of funding. The harbor was last dredged in 2025, with 255,651 cubic yards of sediments removed.

Cleveland Harbor is a deep draft commercial harbor which handled 13.8 million tons of cargo, including iron ore (64%), limestone (16%) and salt (9%) in 2023. Waterborne transportation facilitated by the harbor supports $646.1 million in business revenue, 2,329 direct, indirect, and induced jobs, and $142.6 million in labor income to the transportation sector.

Authorized depths within Cleveland Harbor range from 18 to 29 feet, with the shallowest depths in the Cuyahoga River turning basin and the deepest depths in the entrance channel. The Corps of Engineers maintains these depths to support safe and efficient navigation for large vessels.

Operation, maintenance and dredging of harbors like Cleveland by the U.S. Army Corps of Engineers is critical to the economy of Ohio, the Great Lakes region, and the United States.