Buxton Beach Nourishment Project Update

Posted on September 18, 2026

Great Lakes Dredge & Dock Company has announced that the 2026 Buxton beach renourishment project entered its final phase on Wednesday afternoon, (September 16, 2026), as the contractor completed renourishment along the developed Village of Buxton shoreline and shifted operations northward into the Cape Hatteras National Seashore.

To date, approximately 1.5 million cubic yards of sand—75% of the 2.0-million-cubic-yard total—has been placed on the beach within the project area.

Click here to view the 2026 Buxton beach nourishment project progress map.

With the protective dune and berm in Buxton complete, the remainder of construction activities will consist of widening the beach along a portion of the Cape Hatteras National Seashore. Weather permitting, Great Lakes Dredge & Dock remains on track to complete nourishment by the end of September 2026.*

Buxton Terminal Groin Project Update:

Construction is underway on the trestle in preparation for removing the seaward remnants of the former jetty. Following removal of the old material, new sheet piles will be driven and reinforced with armor stone. The project remains on schedule, with substantial completion anticipated by December 15, 2026, or sooner.