Posted on April 18, 2025
After Hurricane Michael displaced more than 400 million cubic yards of beach shoreline, our team has been working to restore and reinforce the coastline. Over the last several months, we’ve been moving down the beach in 1,500-foot sections — dredging more than 1,000,000 cubic yards of sand from an outside location with the same sand quality and redistributing it along the beach. To date, we’ve rebuilt three miles of 14-foot dunes and extended the beach berm by approximately 175 feet from the seaward toe of the dune, enhancing the shoreline’s resilience.
We’re on track to finish on April 15th – just in time for turtle season.