So far, the town has not taken him up on the offer.

And like last year, boaters and fishermen are pleading for the town to open the marina, particularly since it is the only safe harbor of its size between Buffalo and Dunkirk for boaters to take refuge when storms hit.

Also like a year ago, Town Board members don’t see eye to eye on the marina.

Hosler said the town’s engineer estimated there is 28,000 cubic yards of sand that needs to be removed from Lake Erie. At $12 a cubic foot, that brings the cost to $336,000.

It won’t cost nearly that much, according to Councilman Michael Schraft. He suggested obtaining bids, and if they are more than the $40,000 the town budgeted for dredging this year, the town could turn to the group that came together last year.

Hosler said she does not want to solicit bids if the town has no intention of awarding them. She said the town must solicit bids for any project costing more than $35,000.

Last year’s low bid was $90,000, and the board rejected it because of the high cost. That’s when the businesses and the union stepped up.

There is another possible option. Sen. Charles E. Schumer has called on the U.S. Army Corps of Engineers to repurpose surplus funding to allow for an emergency dredging of the marina.

“Without these funds and the subsequent dredging operations, Sturgeon Point Marina will not be able to open for the 2021 season, depriving thousands of recreational and commercial boaters of a vital summertime resource and a critical safe harbor,” the senator wrote in a letter to the Corps of Engineers.

It’s not just a recreational issue. The Evans Police Marine Rescue and Recovery Unit usually docks its 23-foot rescue boat during the summer at the marina. And Rich Davenport, a Tonawanda fisherman who is on the Erie County Fisheries Advisory Board, told the Town Board last week it is a liability issue.

“We need to get that up and running,” Davenport said. “We understand there is bureaucracy. We also understand this has been an issue for an awful long time.”

Davenport also noted that the town is responsible for the operation and maintenance of the marina through 2035, under separate agreements it struck with the Corps of Engineers and the DEC in the 1980s, when the marina was built with millions of dollars in federal and state funds.

There is an estimated $6.2 million needed in repairs and improvements to the breakwall. The town wants to make the wall at least 2 feet higher, with steel beam reinforcements, to prevent further damage from storms, Hosler said. There also are less-expensive repairs needed at the inner corner.

She said she is hopeful the town will get approval from FEMA soon. She believes construction on the repairs can start this year, and thinks that spending a lot on dredging this year would be throwing good money away.

“It needs to be ready for next year. That’s my goal,” Hosler said. “Sometimes you have to take a short-term loss for a long-term gain.”