Posted on August 10, 2015
By Columb Higgins, ShoreNewsToday
The Strathmere and Whale Beach portion of a federal beach replenishment project was completed on July 19.
Township engineer Paul Dietrich said Monday that all the pipeline has been removed from local beaches. Beach crossovers and dune fence installation still have to be completed in some areas, he said.
The Great Lakes Dredge & Dock Company dredge Illinois has now started beach fill in Sea Isle City. Officials there do not expect their part of the project to be complete until October.