Posted on June 23, 2015
The
Within the working visit framework, the management of MSCC Bronka project realizing company Fenix LLC, gave the guests a presentation concerning construction status of the approach channel, aquatorium, onshore infrastructure, and preparation for launching of MSCC Bronka Phase 1.
Aleksei Shukletsov, Executive Director of Fenix LLC, informed the delegation that the scope of dredging performed by
Shukletsov added that the total scope of dredging to be performed during the navigation period of 2015 is to exceed 13 mln cbm to ensure the depth of the approach canal and the water area of MMPK Bronka of up to 14.4 m, thus making Bronka a deepwater port of