Posted on October 13, 2025
We are undertaking scheduled maintenance dredging works within the Newport Waterways canal estate.
The project works include maintenance dredging in the following locations:
- Kingfisher Canal
- Northern Marina Basin
- Skua Canal
- Curlew Canal
- The intersection between Kestrel Canal and Albatross Canal
- Walkers Creek Canal.
Scope of works
The scope of the maintenance dredging works will encompass:
- preparatory works at the Griffith Road Dredged Material Management Facility
- pre-work hydrographic survey of the dredging areas before the commencement of dredging works
- removal of dredged material by a cutter-suction dredge. This includes the movement of dredged material to the Dredged Material Management Facility
- post-work hydrographic survey of the entire Newport Canal system after dredging works.
Dredging timeline
- Start date: November 2025
- Duration: approximately five months, subject to weather conditions.
- Working hours: Monday to Saturday, 7:00 AM to 6:00 PM, excluding public holidays.
The Newport Waterways canal system is narrow in places. The dredging contractor will ensure that the impact of other vessels’ use of the waterway is minimal.
Location
Newport Canal, Griffith Road, Newport 4020 View map
Location of works
Contact details
Project Officer