Posted on June 28, 2023
The New York Independent System Operator (NYISO) announced it has selected a transmission project to meet the Long Island Offshore Wind Export Public Policy Transmission Need (Long Island Need).
The selected transmission development, Propel Alternate Solution 5, will ultimately benefit energy consumers by providing transmission capability to deliver at least 3000MW from offshore wind sites.
Propel Alternate Solution 5 will add three new underground cables connecting Long Island with the rest of the state and a 345 kV transmission backbone across western/central Long Island.
This will advance the state closer to its goal of 9000MW of offshore wind energy by 2035.
The project will be developed by the New York Power Authority and New York Transco – a partnership called Propel NY.
President and chief executive of the New York Independent System Operator Rich Dewey said: “The selection of Propel Alternate Solution 5 is a critical step forward as the state works to meet its ambitious climate mandates.
“On behalf of the Board, I want to thank all the developers who submitted project proposals, stakeholders who participated in the process and, of course, the NYISO staff for their expertise and dedication.”
The Long Island Need was initially declared by the New York State Public Service Commission (PSC) in a March 2021 order.
That order began a multi-year, joint effort by NYISO’s team of experts, the New York State Department of Public Service, developers, and stakeholders to address transmission needs in and around Long Island driven by the Climate Leadership and Community Protection Act.
This transmission project will offer New Yorkers greater access to diverse and efficient resources. It will also provide effective flexibility under a wide range of operating conditions.
Additionally, Propel Alternate Solution 5 has relatively low procurement, permitting, and construction risks compared to 15 other proposals that were deemed viable and sufficient by the NYISO, it said.
The project is required to be in-service by May 2030 with an estimated capital cost of $3.26bn.
Moving forward, Propel NY is responsible for submitting this project to the appropriate governmental agencies and authorities to obtain approvals and permits to site, construct, and operate the project.
This includes the PSC’s process for siting of major utility transmission facilities under Article VII of the Public Service Law.