Jan De Nul halfway through the immersion operation of the Scheldt Tunnel

Posted on September 22, 2025

We are halfway through the immersion operation of the Scheldt Tunnel!

The fourth of eight tunnel elements has been successfully immersed and positioned on the riverbed of the Scheldt. The operation started in July 2025, and now four massive elements, each weighing 60,000 tons, rest on the bottom of the river.

The remaining tunnel elements will be immersed in the following order: 5, 6, 8, and finally 7. Why end with element 7? Because element 8 connects directly to the fixed tunnel section on the Right Bank. If element 7 were already in place, it would be impossible to sail over it with element 8, as the water is simply not deep enough.

No alternative text description for this image

Together with: BESIX, STADSBADER CONTRACTORS NV, DEME Group, Lantis, IMMONTEC, COTU

Source