Posted on May 5, 2025
Jamaica Beach Nourishment Project
Begins Monday, May 5, 2025
The Beach Nourishment Project will begin on Monday, May 5, 2025, with the delivery of equipment and installation of signage.
- Sand delivery will start on Tuesday, May 6, 2025, at the far west side of the beach.
- Weather conditions may affect the project timeline.
- The project was originally scheduled to begin in Fall 2024.
- Due to circumstances beyond our control, the General Land Office (GLO) contractors were delayed due to shortage of materials needed to begin the project.
Project Phases
- Initial Phase (West of Buccaneer):
- All work will take place west of Buccaneer.
- The beach west of Buccaneer will be closed (see schedule below).
- The beach east of Buccaneer will remain open.
- 2. Second Phase (East of Buccaneer):
- Once work on the west side is complete, activities will shift east of Buccaneer.
- The beach west of Buccaneer will then reopen.
The project is expected to continue through summer 2025.
_________________________________________________________________________
Access Restrictions
During Active Work (Monday–Friday, 7:00 AM – 6:00 PM):
- No vehicle or pedestrian access will be allowed on the active construction side of the beach.
Evening Access (Monday–Thursday, 6:00 PM – 7:00 AM):
- Full beach access will be restored each evening.
Weekend Access (Friday 6:00 PM – Monday 7:00 AM):
- Full vehicle and pedestrian access to the entire beach will be available throughout the weekend.