Posted on October 17, 2025
Key Details
- Start Date: Construction is set to begin the week of October 20, 2025.
- Duration: The sand placement is expected to take about four weeks, depending on weather conditions.
- Sand Volume: Approximately 66,000 cubic yards of sand will be placed on Upham Beach.
Project Context
This project is part of a $125.7 million beach nourishment effort that will place over 2.5 million cubic yards of sand across several beaches.