Posted on May 30, 2022
Work is well underway as the U.S. Army Corps of Engineers, Omaha District, in partnership with our contractors and sub-contractors, are excavating bed rock from the Florence Bend reach portion of the Missouri River near Omaha.
The implementation of the excavation is due to riverbed degradation in recent years, which has lowered water elevation at certain river stages through this reach of the river. This has resulted in insufficient navigation channel dimensions at several locations within Florence Bend. The shallow depths add risk or hinder passage to the nearly five million tons of cargo moving along the Missouri River annually. The goal is to excavate a minimum of 120,000 cubic yards of material, and restore adequate channel parameters for river traffic, by contracts end.
“The navigation channel has experienced some degradation over the past few decades due to all the floods that have happened, and the purpose of this project is to restore the draft for the tows to come through, with the goal being to get back to a 300-foot width and nine-foot depth authorized navigation channel,” Daniel Pridal, Omaha district engineer, said. “We’ve got about 120,000 yards of material to remove and, so far, pretty good progress, but that’s the reason we are out here inspecting the process and following up on it.”
The process to achieve this goal includes excavating high pinnacles of bed rock from the Missouri River one mile downstream of the Mormon Bridge, transporting the rock upstream on barges, and placing that excavated rock on revetments. By bolstering these revetments, this can prevent or minimize future damage during periods of floods or heavy seasonal rains. The bedrock is being moved at a pace of 2000 tons a day and operations run 12 hours a day, seven days a week.
This operation is being executed as a part of ongoing maintenance of the navigation channel, which begins at the mouth of the Missouri River at St Louis, Missouri and extends upstream for 734 miles to Sioux City, Iowa.
The base contract of this $8.2 million project is scheduled to be complete at the end of May, with option one and two portions completed in October 2022.
For additional information on the District’s Missouri River projects visit: https://www.nwo.usace.army.mil/Missions/Dam-and-Lake-Projects/Missouri-River-Navigation/