Posted on January 5, 2017
By Jon Pompia, The Pueblo Chieftain
The Pueblo Levee Dredging and Maintenance Project, which will run through April, is being undertaken to improve the flood carrying capacity of Fountain Creek from the confluence with the Arkansas River upstream to the East Eighth Street bridge.
The work also will see the removal of undesirable vegetation on the east levee embankment (stream side only), on the east bank of the creek and on a portion of the west bank of the creek.
The work is being handled by Sun Construction, which has contracted with the Fountain Creek Watershed, Flood Control and Greenway District.
After the dredging of the creek, the bed material will be hauled by trucks to disposal sites. The work also will include the demolition of two of the abandoned railroad bridge piers.
Truck and equipment access to the creek will be from two staging areas on city property — one at the location off South Joplin Avenue near the abandoned railroad bridge and the second at the west end of East 11th Street.
During the project, the contractor will manage vehicle traffic interactions on public streets and with traffic on the river trail adjacent to the levee. Currently, the bike trail on the east side of the river is closed.
Removal of vegetation on the east and west banks will be limited to non-native, “invasive species” and will not include desirable species such as willows and cottonwoods.
Removed vegetation on the east levee and invasive species will be treated with a herbicide to hinder regrowth.
The removal of vegetation is expected to occur between April and August.
The city will benefit from the delivery of about 55,000 cubic yards of material that will be trucked to sites near Lake Minnequa and near Plaza Verde Park.
While the dredging and demolition will continue through April, the operation will be suspended during the period of higher creek flows — until approximately August and concluding by the end of December.
For additional information about the project, contact Jeff Bailey with the city’s stormwater division at 553-2899.
Source: The Pueblo Chieftain