
Posted on July 11, 2018
By Chabeli Herrera, Miami Herald
Despite a massive dredge project that was completed in 2015, PortMiami is still not wide enough in some areas to accommodate large vessels, making it difficult for cargo and cruise ships to navigate its channels.
The problem with the dredge completed in 2015: timing, said Port Director Juan Kuryla. The $205 million project, which began dredging in 2013, was based on a study completed in 2004 and authorized by Congress in 2007. Since then, cargo ships have outgrown original size projections nearly 50 percent.
To devise a solution, the U.S. Army Corps of Engineers has been allocated $556,250 for a feasibility study regarding port improvements. Susan Jackson, a spokeswoman for the agency, said the study was requested by the port in March because of issues raised by harbor pilots about navigating PortMiami. The study will go before the Miami-Dade County Commission on July 24.
When the port’s depth was studied in 2004, the largest ship expected to pass through PortMiami was 6,600 TEUs, said Kuryla. (One TEU is equal to a standard 20-foot-long, 8-foot-tall shipping container.) The 50-foot dredge completed in 2015 was built to accommodate larger, post Panamax ships with drafts up to 50 feet that became more widely used in anticipation of the 2016 Panama Canal expansion.
Now, ships are even bigger.
“Now we are talking about 13,000 and 14,000 TEU ships that are looking to penetrate the East Coast market,” Kuryla said. “We need to undertake some modifications to the channel, and that’s what this study is going to look at.”
Since mid-2016, South Korea’s Hanjin Shipping Co. collapsed and the cargo industry has consolidated to a half-dozen major players, according to data provider Alphaliner, that now account for nearly 70 percent of the industry. Larger vessels are more cost effective.
That has presented new challenges for PortMiami, which completed the $205 million “Deep Dredge” project that deepened the channel by more than 50 feet in 2015 and allowed the port to accept larger vessels sailing through the expanded Panama Canal. Since the dredge, PortMiami has served nearly 250 post Panamax ships with a deep draft of 39 feet or greater.
“We’re the only port south of Virginia with the infrastructure in place to serve big ships,” PortMiami said in a statement. “Continued improvements are necessary to keep the portcompetitive.”
According to the Biscayne Bay Pilots who navigate PortMiami’s channels, huge cargo vessels with capacity for 11,000 TEUs are struggling to maneuver when entering the port from the ocean through the outer entrance channel.
The Miami entrance challenges lead to delays in port operations. According to PortMiami, those vessels now have to schedule their arrivals weeks in advance.
The study will also analyze other needs too, Jackson said, including widening the Lummus Turning Basin and Fisherman’s Channel for better maneuvering for Post-Panamax vessels and cruise ships. A deepening of the port could also help accommodate a new breed of mega container ships —those with capacities of up to 14,000 TEUs — in the future.
Cruise ships are also experiencing a tight fit in the Lummus Island Turning Basin and in a bend leading from Fisherman’s Channel to Dodge Island Channel. That means the vessels can’t pass container ships docked at berths when they are being loaded, which creates delays, Jackson said.
The Corps would also like to add improvements to the Dodge Island Channel to the federal project, which would allow the port to more efficiently process cruise ships and prepare the port for future cruise industry growth.
Two new cruise terminals, one by Royal Caribbean Cruises and another by Norwegian Cruise Line Holdings, are currently being built at PortMiami and are designed so the port can welcome the lines’ largest cruise ships. In Royal Caribbean’s case, that means its behemoth Symphony of the Seas, which will be the largest ship in the world when it arrives at PortMiami in November.
The port is in talks to add two more terminals, east of the new Royal and Norwegian terminals, at least one of them for MSC Cruises, Kuryla said. The north channel in that area is deep enough for the largest cruise ships on order, he said, but the port wants to enhance the south channel, where smaller ships traverse, to potentially accommodate mid-size ships.
“We are looking medium- to long-term,” Kuryla said.
To analyze the improvements needed, the Corps will conduct a feasibility study over the next three years, at a cost of no more than $3 million. PortMiami estimates that the enhancements from the project could bring in an additional $30 million to $50 million annually. The ability to welcome 14,000 TEU cargo vessels would generate new jobs and growth for Miami-Dade County, the port said.
According to a study conducted by Martin Associates in 2016, the most recent, the port contributed to nearly 45,000 direct, induced and indirect jobs and $7.4 billion in economic impact from business service revenue and re-spending and consumption. In 2017, it also broke a world record by welcoming 5.3 million cruise passengers. PortMiami is projected to host 5.4 million visitors in 2018.
“In order to continue to grow the economic significance of PortMiami, sustained investments in infrastructure are critical. The stronger we are economically, the more resilient we can be as a community,” Miami-Dade County Mayor Carlos Gimenez said in a statement.
The port’s 2015 expansion was one in a string of enhancements for PortMiami that began in 1990. PortMiami’s first dredge was completed in 1993, when it was deepened to 42 feet. A $40 million project to expand the South Harbor was completed in 2006.
The most recent dredge drew criticism from environmentalists who sued the Corps, claiming it violated the Endangered Species Act and caused extensive reef damage. The lawsuit led the agency to agree to embark on an environmental study for a similar dredge at Port Everglades, which will delay the start of that project until at least 2019.
Becky Hope, PortMiami’s chief of planning and property development, said the feasibility study for the new project will include an environmental study to minimize potential impacts.
Total costs for the proposed project are not yet known, Jackson said. PortMiami estimates that because the improvements will only enhance the existing project, they will not cost as much as the previous 2015 expansion. Costs for the project will be shared between federal, state and local funds.
The Corps plans to hold its first public meeting to discuss alternatives and a potential plan in spring 2020.
“The port has an opportunity now that it really never has had before in terms of growing, knowing that the projects will realize immediate benefit for both industries — cruise and cargo — as well as the entire community,” Kuryla said.
Save Our Siesta Sands 2 (SOSS2) said the threat lies in the negative impact on Siesta Key property values, the elimination of the only viable Sarasota boating access to the Gulf and the risk to Siesta Key losing its iconic beach and number one status.
SSOS2 also claims the permit violates several federal laws and has hired a Jacksonville lawyer to try and prove it.
The permit authorizes the project team to take 1.3 million cubic yards of sand from Big Pass to place on the central and southern segments of Lido Key — a plan which is expected to cost around $22 million.
Source: Miami Herald