Colossal construction on Monongahela pumps out water, marking turning point in top U.S. navigation project

Kirk McWilliams and Shawn Soltis, resident and field engineers for the U.S. Army Corps of Engineers Pittsburgh District, stand over the construction project at Charleroi Locks and Dam on the lower Monongahela River in Pennsylvania, Sept. 30, 2021. The Pittsburgh District recently finished building the new lock chamber walls and has emptied it of approximately 20 million gallons of water, a process called dewatering, to allow contractors to begin adding the mechanical inner works of the chamber. The new lock chamber is 84 feet wide by 720 feet long, which will allow a nine-barge tow to lock through in 25 minutes, something that would take more than two hours using the older, smaller lock chamber. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)

Posted on October 6, 2021

PITTSBURGH – The newest navigation lock on the Monongahela River is massive. It can fit nine barges and hold 20 million gallons of water, and it is now finally empty.

Charleroi Locks & Dam

The U.S. Army Corps of Engineers Pittsburgh District pumped out so much water from the chamber that it could fill 30 Olympic-sized swimming pools. Put another way, that amount of water could stage five sea battles inside the Roman Colosseum, which required four million gallons of water to reach a depth of five feet for their famed water battles, according to tribunesandtriumphs.org.

Emptying the chamber is called dewatering, a process of pumping the water back into the Monongahela River.

Charleroi Locks & Dam

“Dewatering the riverside lock chamber is a major turning point in the ongoing construction,” said Kirk McWilliams, the resident engineer with the Pittsburgh District who has been supervising construction at Charleroi Locks and Dam since the beginning.

Construction at Charleroi began in 2004. Once finished, the Charleroi project will cost approximately $1 billion, completed over a span of 20 years, expected to finish by 2024. The federal government funds half of the project’s cost, while the other half is covered by navigation industry through taxes paid on diesel fuel.

Charleroi Locks & Dam

McWilliams said this construction is part of the much larger Lower Mon Project, which is considered the number one inland navigation priority in the country right now by the U.S. Army Corps of Engineers.

“I think the navigation industry will be ecstatic,” said McWilliams of the project once finished.

This is significant for the region since both the Monongahela and the Allegheny rivers are critical to continental navigation.

“We’re the headwaters district. That means we’re the headwaters of the whole inland distribution system all the way down to the Gulf of Mexico. It’s very important,” said Shawn Soltis, field engineer at Charleroi.

Charleroi Locks & Dam

McWilliams compared this project to motorists finally being able to enjoy a new road or bridge after dealing with years of orange barrels, narrowed lanes, and construction crews.

“Everybody knows about infrastructure,” McWilliams said. “It’s a very relevant topic right now. When you think about infrastructure, you think about highways and bridges. Maybe you think about sewer and water lines. But most people don’t associate navigation locks with infrastructure, and this is as vital to the nation’s economy as highways and bridges.”

Yet, twenty years of construction is an especially long time for a navigation project of this type, McWilliams said. In comparison, a similar construction at Braddock Locks and Dam took only six years, just 30 miles downstream.

Charleroi Locks & Dam

The difference is during the Braddock construction, which completed in 2004, the Army Corps had the benefit of a Continuing Contracts Clause. This clause allowed government agencies to award larger, long-term contracts, and pay them yearly, or as funding became available.

Charleroi Locks & Dam

When Congress removed that clause, it complicated matters for mega project constructions like this one. Now, the corps can only contract based on available, annual funding. No longer could the Pittsburgh District award a $200 million contract to a single agency for multiple years of work if the budget was $30 million for that particular project. Instead, it had to break each contract into smaller segments, causing bigger delays. Without this clause, projects became less efficient and more expensive.

“You’ve got redundancy here where you’ve got multiple contractors working on the same feature of work. You’ve got double the cranes. Double the overhead staff. It drives the cost up considerably,” said McWilliams.

Charleroi Locks & Dam

After 17 years of middle and river wall lock construction, emptying the chamber marks a shift toward the finish line at Charleroi, he said.

“It’s a large milestone. We’re turning the page on lock wall construction, and we’re getting into putting all the features that go into making this lock operational,” McWilliams said.

Pumping out the water means engineers can begin working on the inner guts of the chamber, which includes adding the miter gates, the filling and emptying system, culverts, the sills, and new operating equipment.

Charleroi Locks & Dam

McWilliams calls these components the “central nervous system” of a lock chamber, something they could not add if the walled chamber were full of water.

“The new lock is going to be wider than the old lock. It’s going to remove a bottleneck to navigation. It’s going to allow commercial traffic to lock through Charleroi much faster than it currently does,” McWilliams said.

Charleroi Locks & Dam

The chamber is measured 720 feet long by 84 feet wide, allowing a commercial tow with nine barges to lock through in 25 minutes instead of two hours. Previously, the two smaller locks at Charleroi were only 56 feet wide, which meant a tow would have to break up its barges and take multiple trips – back and forth – across the chamber to lock through its full cargo.

The new lock chamber is like a four-lane interstate, versus the smaller chamber being synonymous to a two-lane country road, McWilliams said.

Similarly, a tow would have to perform the same two-hour-plus process again at Elizabeth Locks and Dam, only 18 miles away. Traveling that span of the Monongahela could take five hours.

Once Charleroi is complete, the district will decommission and remove the navigation facility at Elizabeth. Barges will be able to navigate 30 miles nonstop between Charleroi and Braddock, transforming a five-hour navigation stretch into 30 minutes.

“It’s a great feeling to be part of that transformation from paper (plans) to an actual physical project, and that soon we’ll have boats locking through here, to see it in operation,” Soltis said.

Charleroi Locks & Dam

Source