Posted on August 7, 2023
Maldives Transport and Contracting Company (MTCC) has disclosed that the Channel and Maintenance Dredging Project of Baarah island of Haa Alifu Atoll.
MTCC stated that the Channel and Maintenance Dredging Project of Baarah island has so far seen overall 70 percent project progress.
The company has completed channel dredging operations and harbor basin maintenance dredging operations.
Scope of works include, 49,437.5cbm channel dredging operations, 8,600cbm maintenance dredging operations, construction of a 460m geobag revetment and installation of navigational lights.
The value of the project is MVR 14.5 million.